I'm starting to work with Manufacturing for the first time and have a few questions:
Is there a way to show total machining time for a part? If I go into "information" for each operation there is a time listed there but for a large part it's time consuming to go through each operation. Is this time estimate considered more or less accurate? I know I will need to add time for tool changes. I tried modifying the post file to show the time at the end of the program, per these instructions, but it doesn't work:
How do I view the speed/feed data associated with each material when defining the Workpiece? How can a new material be added?
That's all for now; I'm sure I'll have more to come. Thanks!
Is there a way to show total machining time for a part? If I go into "information" for each operation there is a time listed there but for a large part it's time consuming to go through each operation. Is this time estimate considered more or less accurate? I know I will need to add time for tool changes. I tried modifying the post file to show the time at the end of the program, per these instructions, but it doesn't work:
How do I view the speed/feed data associated with each material when defining the Workpiece? How can a new material be added?
That's all for now; I'm sure I'll have more to come. Thanks!