SperlingPE
Structural
- Dec 27, 2002
- 591
I need some information.
Is there documentation that would allow a mason to place fertical reinforcing after the cells are grouted and after the grout has begun to set up (10-30 minutes after the cell is filled)?
My understanding is that reinforcing is in place prior to laying up the units or can be placed after the units are laid up (with the use of positioners). If reinforcing is placed after the units are laid up, grouting is never done before the reinforcing is placed.
Is there documentation that would allow a mason to place fertical reinforcing after the cells are grouted and after the grout has begun to set up (10-30 minutes after the cell is filled)?
My understanding is that reinforcing is in place prior to laying up the units or can be placed after the units are laid up (with the use of positioners). If reinforcing is placed after the units are laid up, grouting is never done before the reinforcing is placed.