Guastavino
Structural
- Jan 29, 2014
- 381
Hi All,
So this isn't exactly a structural engineering question but I'm not sure what forum to use, and since it has structural implications, I figure I'll ask them here:
1. An architect I work for told me that the "air space" in the veneer code (TMS 402 chapter 6) includes the insulation thickness. For example, say you have a 1'-2" nominal masonry wall, 8" CMU, 2" air/insulation, and 4" brick. Let's say you need 2" of insulation for Energy code, so you have a 2.75" air space (But in reality it's close to 3/4") if you assume the mason keeps the 1'-2" wall thickness and you add back the 3/8" from the CMU/brick. Masonry code (TMS402) has a 1" minimum air space per chapter 6. This wall is built ALL the time where I practice. I'm just curious the intent of the TMS code.
2. When you spec a nominal 1'-2" wall as mentioned above, do you detail it (in sections etc.) assuming it's 1'-1 5/8", 1'-2", or something else? I know they can't build it that tight, but I'm curious how others do it. I typically hold the 1'-2" for the purpose of determining working points etc.
3. When you dimension interior walls such as 8" CMU, do the masons you work with know that it's a centerline nominal dimension. I see this only as a problem when you have a string of dimensions crossing 8" walls. If say, a mason built using face to face dimensions, he would lose 3/8" each time and you could have a problem after a dimension string is added up.
With that said, I've only had one issue dimensioning with masonry dimensioning where something like this added up and it was in Revit where revit used ACTUAL dimensions and the precision on the dimension string was set at 1/8th". Then you can image it cut 7.625" in to a 3-7/8" every time and you can imagine that that 1/16th roundup over a string of dimensions had the steel fabricator going nuts. This was the first revit project the company I used to work for did, thus the learning curve. Everything worked out in the end, but was a short nightmare.
Thanks to all.
So this isn't exactly a structural engineering question but I'm not sure what forum to use, and since it has structural implications, I figure I'll ask them here:
1. An architect I work for told me that the "air space" in the veneer code (TMS 402 chapter 6) includes the insulation thickness. For example, say you have a 1'-2" nominal masonry wall, 8" CMU, 2" air/insulation, and 4" brick. Let's say you need 2" of insulation for Energy code, so you have a 2.75" air space (But in reality it's close to 3/4") if you assume the mason keeps the 1'-2" wall thickness and you add back the 3/8" from the CMU/brick. Masonry code (TMS402) has a 1" minimum air space per chapter 6. This wall is built ALL the time where I practice. I'm just curious the intent of the TMS code.
2. When you spec a nominal 1'-2" wall as mentioned above, do you detail it (in sections etc.) assuming it's 1'-1 5/8", 1'-2", or something else? I know they can't build it that tight, but I'm curious how others do it. I typically hold the 1'-2" for the purpose of determining working points etc.
3. When you dimension interior walls such as 8" CMU, do the masons you work with know that it's a centerline nominal dimension. I see this only as a problem when you have a string of dimensions crossing 8" walls. If say, a mason built using face to face dimensions, he would lose 3/8" each time and you could have a problem after a dimension string is added up.
With that said, I've only had one issue dimensioning with masonry dimensioning where something like this added up and it was in Revit where revit used ACTUAL dimensions and the precision on the dimension string was set at 1/8th". Then you can image it cut 7.625" in to a 3-7/8" every time and you can imagine that that 1/16th roundup over a string of dimensions had the steel fabricator going nuts. This was the first revit project the company I used to work for did, thus the learning curve. Everything worked out in the end, but was a short nightmare.
Thanks to all.