nbr1
Geotechnical
- Feb 29, 2008
- 95
I am involved in a project where the Owner would like to omit drilling and blasting as a method for rock excavation; however, rock excavation will
be required for foundations and utilities for numerous(>30)residential structures on shallow foundations (no basements). The site is relatively level with rock near existing grade in some areas (say 1/3 of the site). Rock excavation depths are not likely to be greater than 3 to 5 feet; where required for foundation support or utilities. The rock is limestone (Core Recoverly 10 to 80%; RQD 0 to 40%). SPT values in the limestone range from 50/6" to 50/0" and auger refusal. No coring was performed (although data is available from an adjacent area).
Here is my concern: If we catorgorize excavation as 'unclassified', should we anticipate a changed site condition claim by the Contractor? My worries are that the Contractor will claim that he cannot get adequate 'PRODUCTION' with hoe-ramming or other mechanical means and then claim that it was assumed that mechanical means would be 'productive' since blasting was not permitted. I guess this is not a question of 'rippability' as much as 'practicablity of rippability'; since most materials could probably be ripped if you are willing to pound on the rock for days or weeks. Also, my concern is that the Contractor may claim we did not adequately characterize the bedrock since no coring/lab testing was peformed at the site.
Any comments would be appreciated.
Thx,
be required for foundations and utilities for numerous(>30)residential structures on shallow foundations (no basements). The site is relatively level with rock near existing grade in some areas (say 1/3 of the site). Rock excavation depths are not likely to be greater than 3 to 5 feet; where required for foundation support or utilities. The rock is limestone (Core Recoverly 10 to 80%; RQD 0 to 40%). SPT values in the limestone range from 50/6" to 50/0" and auger refusal. No coring was performed (although data is available from an adjacent area).
Here is my concern: If we catorgorize excavation as 'unclassified', should we anticipate a changed site condition claim by the Contractor? My worries are that the Contractor will claim that he cannot get adequate 'PRODUCTION' with hoe-ramming or other mechanical means and then claim that it was assumed that mechanical means would be 'productive' since blasting was not permitted. I guess this is not a question of 'rippability' as much as 'practicablity of rippability'; since most materials could probably be ripped if you are willing to pound on the rock for days or weeks. Also, my concern is that the Contractor may claim we did not adequately characterize the bedrock since no coring/lab testing was peformed at the site.
Any comments would be appreciated.
Thx,