justbuildit
Civil/Environmental
- Oct 25, 2005
- 17
I have been on several projects that use W14X145 or 120 soldier piles with 3x12 wood lagging. How should the lagging be installed to aid in removal without cutting the lagging. Is there an easy way out there to remove the lagging from the bottom up as backfill progresses? Our guys will just cut the lagging creating shorter pieces that cannot be resused on the next project without reducing the pile spacing. We generally space the piles 8'6" on center and use 8' long lagging. We install the lagging behind the front flange. How do you get the lagging loose to aid removal. Has any tried wrapping wire rope around all the lagging during installation and pulling up with a forklift or crane during removal? Our excavations typically are 10-15 ft deep. Thanks.