mperr97
Computer
- Dec 25, 2002
- 3
I just starting using Microsoft Project 2000, I have a project plan and need to include baseline hours, estimated hours, and actual hours on a project. Is there a way to do all of this and still only calculate the actual number of hours worked?
I entered all of my information into Project and placed a new column called "work" for hours worked so far. When I place a number of hours worked, The number of days is not translating correctly. The days are staying at 1 day. Does anyone know how to fix my number of days?
I entered all of my information into Project and placed a new column called "work" for hours worked so far. When I place a number of hours worked, The number of days is not translating correctly. The days are staying at 1 day. Does anyone know how to fix my number of days?