Beanbag1
Structural
- Mar 12, 2014
- 21
Hello,
I am designing a new steel sheet pile (SSP) retaining wall with grouted tie-backs.
I plan to design the SSP as a cantilevered wall up to a certain height, backfill up to that height, install tie-backs 3-feet below that certain height, test the tie-backs, and then finish the backfilling operation up to the final finish wall height.
QUESTION: Is 3-feet of backfill above the tie-backs a sufficient height of overburden for testing the tie-backs? I am concerned about the wall failing inward as the pull-test apparatus pushes back on the wall. If 3-feet is not enough, what is the minimum height of earth required in order to test the tie-backs?
Thank you.
I am designing a new steel sheet pile (SSP) retaining wall with grouted tie-backs.
I plan to design the SSP as a cantilevered wall up to a certain height, backfill up to that height, install tie-backs 3-feet below that certain height, test the tie-backs, and then finish the backfilling operation up to the final finish wall height.
QUESTION: Is 3-feet of backfill above the tie-backs a sufficient height of overburden for testing the tie-backs? I am concerned about the wall failing inward as the pull-test apparatus pushes back on the wall. If 3-feet is not enough, what is the minimum height of earth required in order to test the tie-backs?
Thank you.