kympen
Civil/Environmental
- Jan 8, 2015
- 2
Can anyone give me guidance or point me in the right direction on the minimum number of days between pours at contraction joints in a 12" RC base slab. The joints have a water-bar as it is in a tank. If the forms are pulled the day after pouring, to reduce shrinkage cracking the specification says seven(7)days must be allowed before casting against the joint. I have looked through ACI 302.1R, 304, 304.2R and cannot find any guidelines relating to this time frame.