MWD123
Structural
- Sep 10, 2021
- 5
Hello
We have a site with a large number of existing piles on it, we are planning to construct a new building that will require large number of new piles to support it.
None of the existing piles will be reused, and the geotechnical engineer is happy that they will not be a factor in their design.
The problem we are facing is how to determine the minimum offset between new and existing to allow for construction tolerances. Although the existing pile heads will be surveyed on site, I expect they could have a verticality tolerance of circa 1:75, as will our new piles, the new piles will also have a tolerance of ~75mm on plan. While we could sum all of these tolerances together, that seems unduly conservative (this would only occur if you had the worst case verticality/positional deviation for both piles, and this deviation occurred in the worst possible direction).
Is there a sensible way of summing various piling tolerances to get a more reasonable offset? Usually I would be happy to take a worst case but the site is so tight that this figure will have a significant impact on the foundation design,
If anyone has any literature or case studies they could share that would be much appreciated.
We have a site with a large number of existing piles on it, we are planning to construct a new building that will require large number of new piles to support it.
None of the existing piles will be reused, and the geotechnical engineer is happy that they will not be a factor in their design.
The problem we are facing is how to determine the minimum offset between new and existing to allow for construction tolerances. Although the existing pile heads will be surveyed on site, I expect they could have a verticality tolerance of circa 1:75, as will our new piles, the new piles will also have a tolerance of ~75mm on plan. While we could sum all of these tolerances together, that seems unduly conservative (this would only occur if you had the worst case verticality/positional deviation for both piles, and this deviation occurred in the worst possible direction).
Is there a sensible way of summing various piling tolerances to get a more reasonable offset? Usually I would be happy to take a worst case but the site is so tight that this figure will have a significant impact on the foundation design,
If anyone has any literature or case studies they could share that would be much appreciated.