lavaghman
Computer
- Jun 12, 2007
- 4
Hi there
Please see the attached screenshot. Have a mismatch between duration total and sum of indivual duration totals.
Under Tools -> Change Working Times and in Options - I have changed the hrs per day to be 7.5 and the hrs per week to be 37.5.
Any help appriciated.
Thanks,
John
Please see the attached screenshot. Have a mismatch between duration total and sum of indivual duration totals.
Under Tools -> Change Working Times and in Options - I have changed the hrs per day to be 7.5 and the hrs per week to be 37.5.
Any help appriciated.
Thanks,
John