doka1
Structural
- Jan 7, 2009
- 66
I am a superintendent for concrete construction and have come across the most bizarre design team. The project is pretty straight forward and involves a concrete topping slab that ramps up. The topping is on top of an existing cast in place concrete parking deck (one way slab). The topping slab is 4" thick and is placed on high density foam. To assist with the extra load from the topping slab, the engineer has added a footing and column mid span underneath one of the existing concrete beams.
We questioned whether or not "ribs" would be required for the topping slab...plans did not illustrate so. It did specify 100 psi hi load, would that help to eliminate the ribs?
Upon saw cutting, excavating, and installing the new Concrete footing, the engineer is not allowing us to strip the forms on the FOOTING for the 3 days! They are requiring concrete breaks before work on the column can progress...I didn't know whether to laugh or get mad. I tried to be professional and cite aci reference material respectfully with no success.
The column requires 4 #6 verticals. We installed #6 dowels and used #7 verticals....the column was rejected because we didnT use #6's...
At this point I really feel like the victim here. I have worked for this owner in the past with success, never with this design firm....
Question is, how would you handle the above situation?
We questioned whether or not "ribs" would be required for the topping slab...plans did not illustrate so. It did specify 100 psi hi load, would that help to eliminate the ribs?
Upon saw cutting, excavating, and installing the new Concrete footing, the engineer is not allowing us to strip the forms on the FOOTING for the 3 days! They are requiring concrete breaks before work on the column can progress...I didn't know whether to laugh or get mad. I tried to be professional and cite aci reference material respectfully with no success.
The column requires 4 #6 verticals. We installed #6 dowels and used #7 verticals....the column was rejected because we didnT use #6's...
At this point I really feel like the victim here. I have worked for this owner in the past with success, never with this design firm....
Question is, how would you handle the above situation?