ben1212
Structural
- Aug 17, 1999
- 9
First of all, thanks to shin25, hokie66, and msucog for your responses to my last compaction questions.
I have several questions this time regarding compaction and settlement.
1) If structural fill (most of the time for me it's some sort of crushed limestone, like a road base material) is compacted to the Standard Proctor within 95% of the dry density what does that number mean in terms of future, long-term settlement of the fill? Would that imply that there is a potential to settle the remaining 5%? And that is in terms of density, how do you equate to depth or inches?
2) What if it is compacted to 100%?
3) Can it be compacted greater than 100% of the dry density?
4) We design a lot of residential projects with slab-on-grade type foundations on hillsides where the downhill foundation wall or grade beam is sometimes in excess of 10 to 15 feet. We do not rely on the compaction of the backfill but instead support the interior grade beams on drilled piers bearing on limestone. Thus, when the structural fill, which was placed in an uncontrolled manner, settles in the long term the drilled piers and perimeter grade beams support the loads. I typically set the "cut-off" depth at about 4 feet of fill. After the fill is deep than that the drilled piers are required. The problem is that this takes a lot of work and coordination with the contractor to ensure that the piers are put in at the right depth. I have had contractors test the compaction of the fill that was placed in an uncontrolled manner and it tests between 95% and 98% with the Standard Proctor, I guess due to the fact of how it was placed. Dump trucks drive over a portion of it while dumping it and then a Bobcat pushes it around. So the fill is actually placed in lifts. Although it can differ from site to site. This is all done within the formwork of the perimeter beams which is usually bags of fill stacked to form the inside face of the grade beams. So I can't imagine that the compaction next to these bags being very good. Anyway, this is not so much a question as an invitation for discussion.
Thanks everyone, I haven't been on Eng-tips in a while but have enjoyed the past few days.
I have several questions this time regarding compaction and settlement.
1) If structural fill (most of the time for me it's some sort of crushed limestone, like a road base material) is compacted to the Standard Proctor within 95% of the dry density what does that number mean in terms of future, long-term settlement of the fill? Would that imply that there is a potential to settle the remaining 5%? And that is in terms of density, how do you equate to depth or inches?
2) What if it is compacted to 100%?
3) Can it be compacted greater than 100% of the dry density?
4) We design a lot of residential projects with slab-on-grade type foundations on hillsides where the downhill foundation wall or grade beam is sometimes in excess of 10 to 15 feet. We do not rely on the compaction of the backfill but instead support the interior grade beams on drilled piers bearing on limestone. Thus, when the structural fill, which was placed in an uncontrolled manner, settles in the long term the drilled piers and perimeter grade beams support the loads. I typically set the "cut-off" depth at about 4 feet of fill. After the fill is deep than that the drilled piers are required. The problem is that this takes a lot of work and coordination with the contractor to ensure that the piers are put in at the right depth. I have had contractors test the compaction of the fill that was placed in an uncontrolled manner and it tests between 95% and 98% with the Standard Proctor, I guess due to the fact of how it was placed. Dump trucks drive over a portion of it while dumping it and then a Bobcat pushes it around. So the fill is actually placed in lifts. Although it can differ from site to site. This is all done within the formwork of the perimeter beams which is usually bags of fill stacked to form the inside face of the grade beams. So I can't imagine that the compaction next to these bags being very good. Anyway, this is not so much a question as an invitation for discussion.
Thanks everyone, I haven't been on Eng-tips in a while but have enjoyed the past few days.