Hi,
I'm currently involved in a refinery revamp project...mech back ground. We plan to do motor solo run test but got to wait for the refinery shutdown/turnaround in Dec 09. The power cable can only be terminated to the panel at substation when the refinery is shutdown.
I just thought perhaps can do motor solo run test earlier than Dec by using temporary power supply via gen set. Consultant say not advisable to do that...
The planned refinery turnaround/shutdown will be 50 mechanical days, quite tight schedule. So whatever activity that can be done Pre-Turnaround is good
Thanks
ppm
I'm currently involved in a refinery revamp project...mech back ground. We plan to do motor solo run test but got to wait for the refinery shutdown/turnaround in Dec 09. The power cable can only be terminated to the panel at substation when the refinery is shutdown.
I just thought perhaps can do motor solo run test earlier than Dec by using temporary power supply via gen set. Consultant say not advisable to do that...
The planned refinery turnaround/shutdown will be 50 mechanical days, quite tight schedule. So whatever activity that can be done Pre-Turnaround is good
Thanks
ppm