CGSmith
Electrical
- Jun 5, 2009
- 19
I have been attempting to use MS Project to track my hours spent on a job, remaining work, percent complete, etc. I was recently asked to start tracking the earned value data as well....So, I saved a baseline, loaded labor rates and got some good data. The problem is, my ACWP does not agree with my actual hours spent on just some of the tasks. In other words, when I multiple labor rate times hours spent, most of the ACWP are correct but some are not. Of course, this is throwing off the cost numbers for the entire job. Any ideas?