FLCIVILENG
Civil/Environmental
- Nov 9, 2006
- 2
I am trying to setup a design schedule in MS Project-- The issues i've run into is that after I establish the precedence diagram/schedule and assign time to each activity(in days), and then resources to each activity, that MS project applies the resource cost(hourly rate) to the entire activity duration. I want to be able to limit the amount of time or work that an activity takes but still maintain the activity duration etc. Anybody have some pointers?