rooster99
Aerospace
- Oct 30, 2009
- 1
Hopefully simple scenario (MS Project 2007):-
I have one task which is a 7 day workshop. Resource 1 (£50/day) will be involved for the first 5 days & then the 2nd resource (£30/day) will be the last 2 days.
How can I enter this resource in days for each resource? I don't want to be entering 5/7's for resource 1 and 2/7's for resource 2 as a percentage as this isn't accurate for costing calculations. Can this be done and if so what is the task type?
Thanks for any help.
I have one task which is a 7 day workshop. Resource 1 (£50/day) will be involved for the first 5 days & then the 2nd resource (£30/day) will be the last 2 days.
How can I enter this resource in days for each resource? I don't want to be entering 5/7's for resource 1 and 2/7's for resource 2 as a percentage as this isn't accurate for costing calculations. Can this be done and if so what is the task type?
Thanks for any help.