wilsonv
Electrical
- Jan 30, 2003
- 33
Hi everybody, I'm working on the calculations for a strip mall consisting of 10 tenant spaces. 2-10kVA Heating units for two spaces and 8-8kVA Heating units for the remaider spaces. Cooling load is less than Heating, so only the heating load is considered. Is there any rules that allow derrating the 10 units in order to size the service or do I have to use 84kVA? Since chances that all units run at the same time are very, very low. Each tenant space will have a panelboard which will feed the Heating units. The supply voltage is 120/208Y 3-phase 4-wire and the Heating units are rated for 208V 1-phase.
Thanks.
Thanks.