UTBKC
Chemical
- Jul 28, 2006
- 2
I have 4 4x6 PSVs located on a 4" nitrogen line, and none of them are spares. As I understand it, all of these PSVs don't actually protect the line and downstream equipment. This is because the process piping area is less than the total area of all of the PSVs. Can credit be taken for just one of the PSVs?
I also want to make sure I'm understanding the area requirement correctly. I'm looking at it as a mass balance. You can't expect more to flow into the 4 4" PSV lines than you have flowing from just one 4" line. However, it would seem as long as the 4" process piping capacity was large enough for the relief load, then flowing throuh just one line to a single PSV (assuming the PSV is large enough) should be fine.
Thanks in advance for the help.
I also want to make sure I'm understanding the area requirement correctly. I'm looking at it as a mass balance. You can't expect more to flow into the 4 4" PSV lines than you have flowing from just one 4" line. However, it would seem as long as the 4" process piping capacity was large enough for the relief load, then flowing throuh just one line to a single PSV (assuming the PSV is large enough) should be fine.
Thanks in advance for the help.