Gaggle
Bioengineer
- Aug 11, 2006
- 2
Is there a way to designate different numbers of hours that individual resources should contribute to a task? I don't want to change the % of a resources time spent on a task, but rather the number of hours each resource puts in to a task that has multiple resources assigned to it.
For example, consider a task with an amount of work set at 20 hours to complete. I want resource A to spend 10 hours on the task, and resource B to spend 7 hours, and Resource C to spend 3 hours each on this task. How can I set up this scenario in Project?
Thank you in advance for your help!
For example, consider a task with an amount of work set at 20 hours to complete. I want resource A to spend 10 hours on the task, and resource B to spend 7 hours, and Resource C to spend 3 hours each on this task. How can I set up this scenario in Project?
Thank you in advance for your help!