MikeLaron
Mechanical
- Nov 18, 2008
- 2
When formulating an Assembly, Sub-Assembly, and parts and material. I set the cost for all the material and parts, to get a total price of that one assembly. My question now, is there a way I can just multiply that cost by inputting a variable somewhere or will I have just have to copy and past that assembly X amount of times?
example
3x Box Assembly cost $150
or
Box Assembly Cost $50
Box Assembly Cost $50
Box Assembly Cost $50
Total $150
example
3x Box Assembly cost $150
or
Box Assembly Cost $50
Box Assembly Cost $50
Box Assembly Cost $50
Total $150