humbug
Industrial
- Jul 18, 2002
- 11
In an effeort to cut out costs our estimating dept. wants to eliminate the NDE budget for performing radiograhpy before PWHT. By B31.1 NDE is required after PWHT for the P4 material group. I am not a big fan of this but in an effort to win more projects I can understand the thinking. We normally perform RT, PWHT, final RT for Code compliance.
We do have some real good welders in the shop with a reject rate hovering around 1%.
We have discussed the addition of a second PWHT cycle and an allowance for rejectable welds and the costs are still less than full RT prior to PWHT.
I'm just looking for various thoughts on the subject.
Thanks
We do have some real good welders in the shop with a reject rate hovering around 1%.
We have discussed the addition of a second PWHT cycle and an allowance for rejectable welds and the costs are still less than full RT prior to PWHT.
I'm just looking for various thoughts on the subject.
Thanks