anbm
Electrical
- Dec 10, 2007
- 36
I have two questions hope some of you can clear for me:
1. I heard some where in NEC or building code indicates when you have a high rise office building, we have
a. Provide an emeregncy generator
b. Separate egress lighting + fire alarm load on a separate ATS from other load.
Do you what particular section of NEC or building code talk about this rule? And how long (hour) should generator require to serve the emergency load in case of loosing normal utility?
2. I know the TVSS using with switchboard rated at 320kA, 240kA, 180kA, etc. Are these standard number? How do we decide what rate of TVSS should we use?
Thank you!
TX-man
1. I heard some where in NEC or building code indicates when you have a high rise office building, we have
a. Provide an emeregncy generator
b. Separate egress lighting + fire alarm load on a separate ATS from other load.
Do you what particular section of NEC or building code talk about this rule? And how long (hour) should generator require to serve the emergency load in case of loosing normal utility?
2. I know the TVSS using with switchboard rated at 320kA, 240kA, 180kA, etc. Are these standard number? How do we decide what rate of TVSS should we use?
Thank you!
TX-man