XR250
Structural
- Jan 30, 2013
- 5,951
The foundation is being dug for a one story, lightly loaded, wood framed building with a crawlspace (34' x 70'). Turns out it is sited on 12 ft. of backfill. The contractor wants to construct the entire foundation on about 50 helical piers. I am not a big fan of constructing a grade beam on a single line of helical piers as I worry about rotation. I have come up with an alternate strategy of using a pair of piers every 11 ft. (see attached).
I still end up with 50 piers but it would seem that this is a more stable system. Any thoughts on this? Also, currently, the piers in each pair are designed to be 24" apart but can be increased a few feet if needed. Is the capacity of the piers reduced due to their closeness? Should I worry about them hitting each other if they are not installed straight?
Thanks!!
I still end up with 50 piers but it would seem that this is a more stable system. Any thoughts on this? Also, currently, the piers in each pair are designed to be 24" apart but can be increased a few feet if needed. Is the capacity of the piers reduced due to their closeness? Should I worry about them hitting each other if they are not installed straight?
Thanks!!