CEguyWSU
Civil/Environmental
- Mar 14, 2014
- 1
So I was given the task of designing a half street improvement that will be demolished and replaced. It's only about 150' stretch. Local jurisdictions require a min. 2% cross slope from CL to gutters and a min. 0.5% flow line in the gutters. Problem is the road is flat, we are talking 0.25%-0.1% throughout the CL of the road and existing gutters. The entire length of the road is sloping in one direction.
If I hold the min 0.5% flow line along the gutter I can tie into the existing with about 3" to spare, but it does not meet the 2% cross slope of the road.
If I hold the min of the 2% cross slope of the road then the gutters end up going below the 0.5% min and I tie in the the existing 6" to high, creating a low point.
This is a small job with a low budget so there is not much else that can be done out there without killing the project. Any advice?
If I hold the min 0.5% flow line along the gutter I can tie into the existing with about 3" to spare, but it does not meet the 2% cross slope of the road.
If I hold the min of the 2% cross slope of the road then the gutters end up going below the 0.5% min and I tie in the the existing 6" to high, creating a low point.
This is a small job with a low budget so there is not much else that can be done out there without killing the project. Any advice?