uasteelcrete
Civil/Environmental
- Apr 4, 2012
- 3
My company is installing a new boiler on an existing slab where the old boiler was installed. I have been looking for examples of how to design an equipment pad that will be installed on an existing slab. I have searched my text books, the ACI and online sources but all I'm finding is elevated slabs, slabs on grade, and slabs on deep foundations. I'm hoping that someone on this forum can give me some advise on where to look for examples of how to design equipment pads on existing slabs. See attachment for a sketch.
The existing slab is a 9 in thick slab on grade with top and bottom rebar mats comprised of #4's @ 12" each way and top and bottom.
The new boiler is approximately the same size and weight as the original. The footprint is 256" x 101" and weight is 162,000 lbs, flooded.
I have installed many such equipment pads but I was not involved with the design. I expect for the new pad I will use #6 rebar dowels into the existing slab and a mat of #4 rebars at 12" o.c. I'm having some difficulty deciding how to properly check this scenario. Can anyone please give me some advice?
Thank you.
The existing slab is a 9 in thick slab on grade with top and bottom rebar mats comprised of #4's @ 12" each way and top and bottom.
The new boiler is approximately the same size and weight as the original. The footprint is 256" x 101" and weight is 162,000 lbs, flooded.
I have installed many such equipment pads but I was not involved with the design. I expect for the new pad I will use #6 rebar dowels into the existing slab and a mat of #4 rebars at 12" o.c. I'm having some difficulty deciding how to properly check this scenario. Can anyone please give me some advice?
Thank you.