ChrisTN
Civil/Environmental
- Feb 23, 2006
- 2
I have a project where the most feasible access to sanitary sewer is to install a pump station to serve the new building and tie into an existing 2" force main that serves the adjacent business. The existing main is 1000' and the new connection will be about 650' from the discharge point (350' from the existing pump). Very low flows and very flat topography along the force main to the discharge point. I have obtained the model number and pump curve for the existing pump and have also picked a preliminary pump design for the new building.
Where I'm getting lost is how to properly calculate the worst case scenario of both pumps operating simultaneously. How do I calculate a TDH at each pump under those conditions? Do I simply add the to operating flows for both pumps and use that flow to determine the friction loss, then check to see if that point is still on the curve for each pump? I'm rather green when it comes to pump station design , so any nudge in the right direction would be greatly appreciated. Thanks.
Where I'm getting lost is how to properly calculate the worst case scenario of both pumps operating simultaneously. How do I calculate a TDH at each pump under those conditions? Do I simply add the to operating flows for both pumps and use that flow to determine the friction loss, then check to see if that point is still on the curve for each pump? I'm rather green when it comes to pump station design , so any nudge in the right direction would be greatly appreciated. Thanks.