Buleeek
Structural
- Sep 5, 2017
- 98
Hi everyone,
I am to design a new 4-story building. It is going to be a row house in NYC and it will be adjacent to the existing row house. It seems the previous building has been demolished together with foundation and the hole filled.
1. The new house wall will be on the property line each side.
2. We do not know much about the existing foundation - no size, material or elevation. I would assume it is concrete and it encroached the property line.
3. The existing building is about 100 years old with clay brick walls
4. My concern is, the part of the new wall will rest on the existing foundation.
5. In the attachment I presented two options: dowel new mat foundation to exisitng footing, or cantilever the mat over the existing footing without touching anything what is existing.
6. We have a soil report:
6.1 The soil capacity is as follows:
The first 4-6 feet is fill - probably filled after demolition. Anyway, no use
below 6 ft -> 1.5 tons
below 10 ft -> 2 tons
below 15 ft -> 3 tons
6.2 no water was found
My idea is to pursue with the option B (cantilever mat foundation)
Can you look at my sketch and help with the following:
7. Which option seems more suitable for this situation
8. Suggestions on the cantilever mat foundation: shape, reinforcing, etc.
9. What should I know about row houses built over 100 years ago
Thank you in advance.
Buleeek
I am to design a new 4-story building. It is going to be a row house in NYC and it will be adjacent to the existing row house. It seems the previous building has been demolished together with foundation and the hole filled.
1. The new house wall will be on the property line each side.
2. We do not know much about the existing foundation - no size, material or elevation. I would assume it is concrete and it encroached the property line.
3. The existing building is about 100 years old with clay brick walls
4. My concern is, the part of the new wall will rest on the existing foundation.
5. In the attachment I presented two options: dowel new mat foundation to exisitng footing, or cantilever the mat over the existing footing without touching anything what is existing.
6. We have a soil report:
6.1 The soil capacity is as follows:
The first 4-6 feet is fill - probably filled after demolition. Anyway, no use
below 6 ft -> 1.5 tons
below 10 ft -> 2 tons
below 15 ft -> 3 tons
6.2 no water was found
My idea is to pursue with the option B (cantilever mat foundation)
Can you look at my sketch and help with the following:
7. Which option seems more suitable for this situation
8. Suggestions on the cantilever mat foundation: shape, reinforcing, etc.
9. What should I know about row houses built over 100 years ago
Thank you in advance.
Buleeek