Hi all,

My colleague has made a one dimensional settlement estimation and has gone on 6 weeks leave and I cannot get the same result as him but am not confident in my result. Any help on where one I am wrong/right would be great.
We have 2m of sand overlying 1m of clay over rock. Water table is at 0.5m depth. We are adding 2.5m of fill to the site. I am trying to estimate settlement. It is concept design so does not have to be super detailed. Profile Follows:

2.5m Fill to be added to the site (Total Unit weight 20kN/m3)
2.0m Sand (Total Unit weight 19kN/m3)
1m Clay (Total Unit weight 18.2kN/m3), w=28%, Cc=0.6, Cr=0.1, Pre-consolidation Pressure =50kPa
Bedrock

I have attached my working out, I estimated approx 15mm of settlement compared to his estimation of approx 80mm. If someone could let me know if I am correct that would be great. He is much more experienced in this field so I am hesitant to dismiss his calculation.
 
Replies continue below

Recommended for you

I am a Geologist rather than a geotechnical Engineer so I'm sorry if this is an elementary question.
 
SciGeo,

I did the calculation using the data you provided. Seems the settlement you calculated is right. I didn't find anything wrong. May be the other person did not consider the over consolidation into the settlement calculation. That could be the reason for higher number in his case.

NT
 
Status