Hello,
When one wants to design any equipment, we define the OPERATING (which are the real ones) and the DESIGN (which are with 5% or 10% more to the operating ones) values of T and P.
I thought that :
OPERATING values = DESIGN values
OVERDESIGN values = DESIGN values + 5/10%
But I think it's false...My boss said to me:
OPERATING values = Real values found in calculations
DESIGN values = OPERATING values + 5/10%
What do you think?
Thanks a lot!
Méli
)
When one wants to design any equipment, we define the OPERATING (which are the real ones) and the DESIGN (which are with 5% or 10% more to the operating ones) values of T and P.
I thought that :
OPERATING values = DESIGN values
OVERDESIGN values = DESIGN values + 5/10%
But I think it's false...My boss said to me:
OPERATING values = Real values found in calculations
DESIGN values = OPERATING values + 5/10%