Hello everyone,
The detention basin has an outlet structure of a 3' x 3' box, with a V-notch weir on the entrance side and a 12" RCP stubbed into the opposite wall. I work with HEC-HMS. The pipe has a very flat slope (0.26%); it has tailwater. How would I figure the discharge going through the V-notch weir and over the top of the box - all before flowing into the pipe? Will HMS work? Or would you rather I use some other software or do hand calculations?
Thank you,
Bills Sis
The detention basin has an outlet structure of a 3' x 3' box, with a V-notch weir on the entrance side and a 12" RCP stubbed into the opposite wall. I work with HEC-HMS. The pipe has a very flat slope (0.26%); it has tailwater. How would I figure the discharge going through the V-notch weir and over the top of the box - all before flowing into the pipe? Will HMS work? Or would you rather I use some other software or do hand calculations?
Thank you,
Bills Sis