jgailla
Geotechnical
- Dec 23, 2004
- 896
I just became involved with a renovation project. The existing structure is two-story masonry on shallow footings. An elevator is to be added to the side of the existing building. Originally, the elevator pit and walls were to rest on a mat bearing three feet below adjacent grade. The contractors dug to this three feet and hit a layer of sandy clay. The top layer was fine sand. They came back the next day to find the hole a foot deep in water. They expected to dig below the sandy clay and encounter sand which could be dewatered. They went down to 10 feet below adjacent grade (of course without adequate supervision), didn't hit sand, and called us. I did one auger boring, and hit sand at about 13 feet below adjacent grade. Further excavation is impractical, and I am suspicious the existing building will undergo detrimental settlement already due to the overexcavation. They want to remove standing water, strip the top 6" of soil, and place gravel (57) into the hole. I am concerned about fines migration and unbalanced pore water pressure, which can be solved with a geofabric, and dynamic loading on what is essentially a gravel column held laterally by existing soils. Dewatering is a problem due to the high groundwater level (about 4 to 5 feet below ground surface now) and the high fines content of the sandy clay. I need to write a proposal for fixing the problem reasonably, and I'm not even sure what tests I want to run. We'll do an SPT to 30 feet to get some general information.