fyaure
Civil/Environmental
- Oct 25, 2004
- 23
If there is a pavement which has been made 10 years back but none of its design specifications and other design data are avaiable now. Traffic has increased tremendously over these years. the exisiting pavement does show some stress cracks but is still fuctioning.
So, my question is is there any standard conservative procedure to assume some original design values, calculate percent damage and then design an overlay?
I guess there are some other criteria I will have to address, please tell me what else I need to know to do that?
So, my question is is there any standard conservative procedure to assume some original design values, calculate percent damage and then design an overlay?
I guess there are some other criteria I will have to address, please tell me what else I need to know to do that?