STrctPono
Structural
- Jan 9, 2020
- 703
For as long as I've been working for my current company, the standard of practice for CIP drilled shafts has been to have the Contractor overpour the shaft equal to the diameter of the shaft. We then have them come back later and demolish the shaft down to the finish top of shaft elevation. The theory being that the upper 1.0 * diameter of the shaft is usually junk concrete due to segregation. We've done it for every job and every shaft. I had a recent project where I had a chance to see some core strength and density results for the in-situ material in the upper 3ft of a 5'-0" diameter shaft and for the most part it did not seem as if the theory of segregation in the top of the shaft was true. Has the more prevalent use of SCC's in deep foundations made this standard of practice obsolete? Do any other firms do this?