TripleAYUDA
Geotechnical
Dear all
I am the client's representative, working with a 2 story building that was initially designed to be supported on a shallow foundation, no geotechnical investigation was carried out and it was simply assumed that the ground is dense sand with an allowable bearing capacity of 100 kpa.
Once I was hired for the project I immediately requested a soil investigation which in turn we found out that the soil is made of 6 m of compressible clay followed by 6 m of dense sand. SPT values in the clay layer range between 5 - 15 and 30 - 60 in the sand layer, with groundwater level close to the surface at 2 m. As a result pile foundation was chosen.
The designer is "a structural engineer", initially he was pressing that the shallow foundation will work but consolidation settlement is about 55mm. At the same time, he does not have experience in pile design. We have lateral loads up 700KN which also need to be analyzed. The designer requested additional compensation for the new foundation design which we do not agree with as it was all his fault.
I would like to hear your feedback and experience in a similar situation
Thanks
I am the client's representative, working with a 2 story building that was initially designed to be supported on a shallow foundation, no geotechnical investigation was carried out and it was simply assumed that the ground is dense sand with an allowable bearing capacity of 100 kpa.
Once I was hired for the project I immediately requested a soil investigation which in turn we found out that the soil is made of 6 m of compressible clay followed by 6 m of dense sand. SPT values in the clay layer range between 5 - 15 and 30 - 60 in the sand layer, with groundwater level close to the surface at 2 m. As a result pile foundation was chosen.
The designer is "a structural engineer", initially he was pressing that the shallow foundation will work but consolidation settlement is about 55mm. At the same time, he does not have experience in pile design. We have lateral loads up 700KN which also need to be analyzed. The designer requested additional compensation for the new foundation design which we do not agree with as it was all his fault.
I would like to hear your feedback and experience in a similar situation
Thanks