afocuf
Materials
- Jan 17, 2008
- 11
Hello All,
I work for a consultancy firm. A client has requested that we prepare a WPS for girth welds in API 5L X65 pipe (25mm thick), to be qualified according to ASME IX. The client also requested that we source the material to be used for the test pieces. These will then be welded and tested by our client.
I am trying to source to source short lengths of X65 pipe, but I can only get quotes for entire pipe lengths (11m). Th eclien tdoes not have material in stock as the WPS is not requsted for specific project, but it is being qualified to 'fill some voids' in their current WPS/PQR collection. We have a suitable pipe end left from a previous project, but this is 30" OD and manual welding is required (GTAW+SMAW); it would be impractical and in my opinion unnecessary to weld the entire weld circumference.
My intention is to use the 30" OD pipe, but only weld one half from 6 to 12 o'clock (5G test position, vertical-up progression), the remove specimens as follows:
- Tension test: as per QW-463.1(e)
- Bend test: two specimens from two of the four locations shown in QW-463.1(e) (rather than one specimen per location)
- Impact test: all specimens taken from one of the areas in QW-463.1(f)
If we welded the entire pipe circumference, we would weld two 'identical' halves in the 5G vertical-up position, so welding and sampling only one half of the pipe would not make a significant difference to the test results.
I have searched ASME IX's intepretations, but I could only find references to performance qualification using two welders (each welding one half of the pipe). I guess because no one in their right mind would weld a 30" OD pipe for a procedure qual, but we do not see to have other options.
Is anyone aware of interpretaitons that address this scenario or do you have previous experience with a similar situation?
Thanks
I work for a consultancy firm. A client has requested that we prepare a WPS for girth welds in API 5L X65 pipe (25mm thick), to be qualified according to ASME IX. The client also requested that we source the material to be used for the test pieces. These will then be welded and tested by our client.
I am trying to source to source short lengths of X65 pipe, but I can only get quotes for entire pipe lengths (11m). Th eclien tdoes not have material in stock as the WPS is not requsted for specific project, but it is being qualified to 'fill some voids' in their current WPS/PQR collection. We have a suitable pipe end left from a previous project, but this is 30" OD and manual welding is required (GTAW+SMAW); it would be impractical and in my opinion unnecessary to weld the entire weld circumference.
My intention is to use the 30" OD pipe, but only weld one half from 6 to 12 o'clock (5G test position, vertical-up progression), the remove specimens as follows:
- Tension test: as per QW-463.1(e)
- Bend test: two specimens from two of the four locations shown in QW-463.1(e) (rather than one specimen per location)
- Impact test: all specimens taken from one of the areas in QW-463.1(f)
If we welded the entire pipe circumference, we would weld two 'identical' halves in the 5G vertical-up position, so welding and sampling only one half of the pipe would not make a significant difference to the test results.
I have searched ASME IX's intepretations, but I could only find references to performance qualification using two welders (each welding one half of the pipe). I guess because no one in their right mind would weld a 30" OD pipe for a procedure qual, but we do not see to have other options.
Is anyone aware of interpretaitons that address this scenario or do you have previous experience with a similar situation?
Thanks