Engeslam
Petroleum
- Jul 19, 2012
- 5
dear all
I need to down load reference for the max PPV on pipeline results from blasting
I need the exact reference and the value
For x52 pipeline of buried under depth 1 meter and having being subjected for vibration from blasting of charge 3 tons at 30 meters away from pipe center line
Resulting on PPV equals TO 27 mm/s
I need to down load reference for the max PPV on pipeline results from blasting
I need the exact reference and the value
For x52 pipeline of buried under depth 1 meter and having being subjected for vibration from blasting of charge 3 tons at 30 meters away from pipe center line
Resulting on PPV equals TO 27 mm/s