Hi, we have a site with 30 feet of peat over 70 feet of 100 blow count till.
We are at a Site Class E due to the peat with a thickness of 10 feet and M%>40; PI>20, Su<500psf per the code.
However when we install grouted rock piles through the peat on a 10' x 10' grid, and no longer have a continuous layer of M%>40; PI>20, Su<500psf soil, we can increase the Site Class to a C correct? As the average blow count will be about 70.
Anyone have experience or can offer any guidance on this?
Thank you