NKT
Structural
- Dec 8, 2003
- 59
I am under the impression that the Pre-Engineered Metal Building (PEMB) manufacturers typically provide unfactored loads, and it is the foundation designer's responsibility to apply the appropriate load factors and combinations to design the foundation system.
One of my supervisors recently expressed the opinion that the PEMB manufacturer should provide the factored and combined loads.
I'm looking for other opinions on who should be doing the factoring and combining for PEMB foundation design, and the reasoning behind the opinions.
Thanks
-NKT
One of my supervisors recently expressed the opinion that the PEMB manufacturer should provide the factored and combined loads.
I'm looking for other opinions on who should be doing the factoring and combining for PEMB foundation design, and the reasoning behind the opinions.
Thanks
-NKT