Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

PEMB Roof Live Load Reduction 1

Status
Not open for further replies.

ARMeerkat

Structural
Oct 24, 2010
2
I've spent 25 years as a structural engineer designing just about every type of commercial and industrial buildings. These buildings include PEMB's. While I've never designed a full PEMB, we have specified hundreds of them and provided the foundation design to support them. One question is always asked by the PEMB manufacturer, "Is the roof live load reducible on the main frames?" It's always bothered me that they feel the need to ask this question, and now I've figured out why.

Whenever checking the roof load capacity of an existing PEMB we can never get the roof purlins (z-purlins) to pass. The design load book that we utilize is the Light Gage Structural Steel Framing Design Handbook (LGSI). I can never get the example problems to match up with the actual design provided by the PEMB manufacturer. I've always assumed, like others, that this is due to some hidden code provisions, or maybe due to actual testing of the purlins. While recently going over the design of an existing PEMB, and once again knowing that the purlins would not pass code, my curiosity got the best of me and I started researching to try and find the answer as to why. The following is a narrative of my thought process and what I found.

The load tables for the z-purlins are broken down into simple-span, two-span, four-span, and six-span conditions. Each of these span conditions is further broken down based on the length of the end laps on the purlins. The premise being that the more end lap you have the more continuity you have, therefore more load capacity and less deflection. So, even though the typical purlin span is only 25 feet, the capacity is increased as though it is continuous over multiple spans. And this is what got me to thinking... if the PEMB manufacturer is assuming the purlin to be continuous over multiple spans, could he also be assuming that the purlin is a single continuous member over the length of the building? If they are assuming a single continuous member over the length of the building, then the tributary are of that purlin would be great enough to justify a roof live load reduction.

So, we puled out three different PEMB projects from three different PEMB manufacturers. All three buildings had the same roof dead load and standard 20-psf live load requirements. The projects were also in three separate states, which became very important. After running the numbers based on the PEMB shop drawings, we could only get one of the buildings purlin design to pass. The other two buildings were then recalculated using a purlin tributary area based on the building length and purlin spacing. We reduced the roof live loads accordingly and checked the purlin design against the LGSI Handbook. Both of the buildings purlins passed within a couple of percent (definitely an AH-HA moment). The difference in the building in which the purlins did pass code is that it is located much further north and had a snow load of 20-psf, which is not reducible, and therefore could not be taken advantage of.

When the PEMB manufacturer asks "Is the roof live load reducible on the main frames?" what they are really doing is omitting the roof purlins from the question. Why ask specifically about the main frames only? Why not just ask if the roof live load is reducible per the code? It is a very dishonest question, designed to create a loop hole by elimination. Don't ask, don't tell.

When a PEMB bulding is 200-ft long and the roof purlins are spaced 4-ft on center (very common) the purlins tributary area (per the PEMB) is 800-sf. The PEMB manufacturer reduces the purlin design roof live load from 20-psf to 12-psf, and never mentions a word about it. We've always thought that PEMB's were deisgned to a frogs hair, but it turns out it's even less than that. Prove me wrong.
 
Replies continue below

Recommended for you

Interesting perspective. If the purlin is not continuous over the length of the building can you actually use the entire building length x the spacing to calculate the area? I'd tend to think that's not the intent of the code prescribed LL reduction.
 
I agree - it seems a bit fishy. You can still have localized full design loads on your roof. That's why it's okay for columns and girders - it's localized and won't have a significant effect on any part of the member. But if you have a full 20psf live load on one bay of your building, the localized effects will exceed the limits for the purlin in that area.

Not saying you're wrong ARMeerkat. Indeed, it sounds like you found an interesting piece of the puzzle.

There are a couple of PEMB guys here. Hopefully one of them can shed some more light on this.
 
Not to highjack your thread but I did a project a long time ago where a PEMB building had the roof blown off and some purlins damaged. I used US Cold Form steel code for the design. The issue I had was with unbraced length for bending. What I found was that testing of the roof, clip and purlin is necessary to prove the unbraced length (Lb) if you want to use something less then the full span. As I recall this was particular to standing seam roofs with hidden clips.

I though this very odd and even talked to technical group at AISI and asked what happens when a PEMB building roof deck is replaced. If you strictly follow the code you would either have to but the clips and roof panel from the original manufacturer or check the purlins - which will likely fail due to increased Lb.

In my case I added additional supports to cut the unbraced length to the point where the purlin would pass.

I am not familiar with Light Gage Structural Steel Framing Design Handbook (LGSI) but I wonder if the testing is one way the manufactures get to an acceptable design in addition to the reducible roof live load you mention above.
 
@ARMeerkat, I agree with your conclusion as I have done a similar check in the past and came to the same conclusion. When I asked about it, basically what I got was it's the industry standard of care (and they won't change it because they would not win projects) and that since it's a single member spanning the full length then the trib is based on such length. I however don't agree with this as the members are not significantly rigid enough to distribute the loading equally to the supports and therefore believe these should be designed as single, localized, spans.

I have found it pretty much useless to question PEMB designers as they cannot even follow a similar standard in providing us loading in a comprehensible manor. I recently did a foundation design for a small 40x40 symmetrical building with portal frames both directions and ended up with completely different size foundations at every column based on how they presented the loads and load cases, comes to find out after talking with the PEMB engineer, that they don't always correlate the load cases for each direction analyzed and WL1 for one direction could be wind going N-S, however WL1 for the other direction could be E-W with WL2 being the N-S direction - how would I know to combine WL1 with WL2 at the moment frames to get the correct reactions under the same wind load direction.
 
Thanks for looking this over. I'm a little nervous about how profound this could be. Feel like I'm starting a race war between SE's and the PEMB industry.

Rabbit12 - On shop drawings, the purlin gage actually changes across the building depending if it's an interior vs exterior bay. Not sure how they could legitimately argue that it's a continuous member.

phamENG - I agree about the localized loading. The intent of the Code is that there's no reduction on secondary members.

Another clue is that the light gage truss rep stated that he can't compete with PEMB's down south. He has no problem up north, but no luck in the south. I figure that is due to the northern snow load > 20 psf that can't be reduced.

When I've denied the PEMB to reduce the live load on the main frames (which they didn't complain about) the result is that the main frames are designed for a higher load than the purlins. Not good.
 
How is partial loading not governing the purlins if continuous and how could you possibly reduce live load for partial loading?
 
I would just answer, or specify in your project proposal, that roof live loads are not reducible. Period. These things are skinny enough without tweaking that. But saying that, where I am, wind uplift always controls and PEMB's don't exist, so my opinion is of little value for you.
 
It does seem a bit fishy reducing the load by that..

Though in this part of the world live load of 20-psf is a fairly onerous roof load for typical roof of a PEMB. And like hokie66 said wind uplift governs. (Both because high load and because Lb.)

Is there any particular reason why such a high live load is used? Snow? (I note that you do have a "northern snow load > 20psf").
 
What part of the world is that human909? And what is the typical roof live load used instead?

Snow is usually treated separately from roof live load in the USA, as the latter is geared towards maintenance/construction activities on the roof and is independent of climate.

 
stucbells said:
What part of the world is that human909? And what is the typical roof live load used instead?
Australia. I believe hokkie66 is also Australia or New Zealand but I don't want to speak for him.

Our live load is "about" 0.35kPa or 7.3psf. More precisely:
"(1.8/A + 0.12) but not less than 0.25, A = the plan projection of the surface area of roof supported by the member under analysis, in square metres."
There is also a separate point load requirement of 1.1kN (cladding) or 1.4kN (members).

Obviously all our loading codes differ here and there but largely there similarities a more than the differences. This difference though I find fairly significant so I thought to add my comments. It turns out that out of codes compared, ASCE and AS codes differ by the greatest amount at typical tributary areas. (See page 26)
 
PEMB Engineer here. I can't answer for all the industry, but I can for the one I work for, which is one of the major suppliers. I do work in areas where snow usually controls.

1) Cold form member design is based off AISI S100. I have never used or heard of the LGSI Handbook.
2) Purlin strength is based off roof panel type. There are different capacities for through-fastened systems (deck, ribbed panel) as opposed to standing-seam roofs. The capacity for standing seam roofs is usually a %-based of through-fastened based off testing. Interior panel can also increase the strength.
3) Purlin tributary area is (Bay * Purlin spacing), with the exception for wind based off C&C loading areas (L3/3 usually controls). Live load should never be reduced for a single purlin unless it's area is large enough in that bay, in which case the partial loading cases are checked.
4) Main frames sometimes will have the load reduced according to tributary area, especially in areas with low snow. Again, where I work Pmin is usually 20 psf as well, so there's no point in reducing the live load.
5) I believe most PEMB engineers would disagree on the tributary area of the purlin being (Building Length * spacing).

PEMBs ask about the live load reduction so the roof isn't underdesigned by assuming it is when it actually isn't.

Aesur said:
I have found it pretty much useless to question PEMB designers as they cannot even follow a similar standard in providing us loading in a comprehensible manor

I agree, I have a hard time figuring it out as well. Hence the problem with using program where the output generation was pioneered in the 80s, and hasn't been changed much since.
 
@Anonymous_ENG, this is some great information, thank you!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor