bearjew
Structural
- Apr 2, 2015
- 27
Hi all,
Let's say we have a PEMB structure with large kickout forces at the base of each rigid frame. These rigid frames are supported on column pedestals and isolated footings (non-moment resisting). If this is the case, it seems we have (2) ways to resist the kickout forces, either hairpins into the slab or tension beams that tie together each end of the rigid frame. In either situation, it is very difficult to get the column pedestal to check OK with regards to shear breakout following Appendix D of ACI.
I understand that many people on this forum have differing opininons on the effectiveness of hairpins, but for the sake of argument lets assume we went with the tension beams. If we develop our tension beam reinforcing fully into the pedestal and 'hook' the pedestals vertical dowels, is shear breakout still a controlling failure mechanism? The way I am imagining this situation is that the thrust gets transferred thru the PEMB anchor bolts as shear into the vertical dowels. The vertical dowels act together due to the ties spaced vertically. If our tension beam is then developed into the pedestal, wrapping the pedestal cage, no shear breakout?
Let's say we have a PEMB structure with large kickout forces at the base of each rigid frame. These rigid frames are supported on column pedestals and isolated footings (non-moment resisting). If this is the case, it seems we have (2) ways to resist the kickout forces, either hairpins into the slab or tension beams that tie together each end of the rigid frame. In either situation, it is very difficult to get the column pedestal to check OK with regards to shear breakout following Appendix D of ACI.
I understand that many people on this forum have differing opininons on the effectiveness of hairpins, but for the sake of argument lets assume we went with the tension beams. If we develop our tension beam reinforcing fully into the pedestal and 'hook' the pedestals vertical dowels, is shear breakout still a controlling failure mechanism? The way I am imagining this situation is that the thrust gets transferred thru the PEMB anchor bolts as shear into the vertical dowels. The vertical dowels act together due to the ties spaced vertically. If our tension beam is then developed into the pedestal, wrapping the pedestal cage, no shear breakout?