vm101
Structural
- Oct 26, 2017
- 4
Hi, I am supporting a project involving new piping through an existing 6" precast panel in a steel "butler" building (built in 1988). Contractor needs to make an opening for a 24" pipe (opening size will be ~26" diameter). Challenge is the only location for the pipe is at an elevation that it will interfere with the girt for the lower precast panel. See attached sketches. The panel is secured to the girt using Z clips that are welded to embeds in the panels. Contractor is recommending lowering the girt (~12") and reattaching the panels with modified (elongated) Z clips that would be welded to the existing embeds. Additionally, the diagonal braces would be cut and reattached to the girt and RF columns (shown in Option 1). Another suggestion (see Option 2) is to leave the girt in place so as not to disturb the majority of the panel attachments. To allow the pipe to pass through, an open square frame would be welded to the modified girt. Any panel connections disturbed by the removed section of the girt would be reattached with modified Z clips as suggested in Option 1. Biggest concern is panel attachment, not modification to girt. Location is remote and material options are limited (i.e., will take at least 3 months to receive materials after fabrication). Questions: 1) Which option seems more viable and less risky to future performance of panel? 2) W14x22 is not available so on-site fabrication of "square" would be necessary. We are looking for steel that could be used to fabricate the square to match the I beam's dimensions. If this is not possible, would HSS be acceptable?