Nuccio
Geotechnical
- Sep 18, 2008
- 20
Just a quick question. I have done a search on this site regarding permanent solder pile walls and precast lagging and it seams it is only done as a bottom up method which I understand why. My question is can a soldier pile wall be built top down as usual but have the timber lagging back lagged against the rear flange and then install the precast lagging bottom up backfilled with gravel and a Mira drain material?