sathishsusa
Petroleum
- Jun 27, 2015
- 6
Dear Experts,
I'm currently working on an upstream oil and gas project where we are conducting a BIDI pigging operation on a 16" MOL line that spans 50 km. I need help creating an Excel sheet to calculate the estimated time of arrival (ETA) for the pigging operation based on the following details:
Pipe diameter: 16" OD (406.4 mm)
Wall thickness: Minimum 15.9 mm, Maximum 30.2 mm
Length: 50 km
Gas-Oil Ratio (GOR): 353
Sealine Pressure: 34.32 BAR
Arrival Pressure: 26 BAR
Flow Rate: 19500 BBL/DAY
Pig Launched Time: 02-08-2024
Pig Arrival Time: ??
Could you help me with this challenge?
I'm currently working on an upstream oil and gas project where we are conducting a BIDI pigging operation on a 16" MOL line that spans 50 km. I need help creating an Excel sheet to calculate the estimated time of arrival (ETA) for the pigging operation based on the following details:
Pipe diameter: 16" OD (406.4 mm)
Wall thickness: Minimum 15.9 mm, Maximum 30.2 mm
Length: 50 km
Gas-Oil Ratio (GOR): 353
Sealine Pressure: 34.32 BAR
Arrival Pressure: 26 BAR
Flow Rate: 19500 BBL/DAY
Pig Launched Time: 02-08-2024
Pig Arrival Time: ??
Could you help me with this challenge?