Hi,
Can someone brief me the criteria of pile set and pile load test for friction pile and end bearing.Please correct me if im wrong as well.
Friction pile - no set taken during driving, wait for at least 2 weeks for dissipation of negative pore water pressure n mobilisation of the friction then conduct the static load test/PDA test.
ENd bearing - set taken during driving (based on Hiley formula), static load test could be conducted the very next day.
Any additional information that i should know or please correct me when im wrong. i'm here to learn.![[bigsmile] [bigsmile] [bigsmile]](/data/assets/smilies/bigsmile.gif)
Can someone brief me the criteria of pile set and pile load test for friction pile and end bearing.Please correct me if im wrong as well.
Friction pile - no set taken during driving, wait for at least 2 weeks for dissipation of negative pore water pressure n mobilisation of the friction then conduct the static load test/PDA test.
ENd bearing - set taken during driving (based on Hiley formula), static load test could be conducted the very next day.
Any additional information that i should know or please correct me when im wrong. i'm here to learn.