kieran1
Structural
- Feb 27, 2002
- 178
I have a situation where load bearing piles have been installed behind a proposed jetty. The contractor has said the piles were installed to refusal, which I doubt.
It is proposed to dredge the area under the piles after a concrete beam is cast, to a level 6.0m below water level. The piles are 11.8m long and top of pile level is 5.73m above water level. This leaves an embedment depth of only 70mm.
This is my concern. I was not involved until after the piles were installed. My thoughts are to not allow any dredging, but this will render the project unworkable.
Anyone any suggestions.
I'm thinking of sand bags in front of the piles to prevent the soil in this area from being removed. This is in Africa so tremie concrete and any solution which requires western technology is not possible. The jetty line is only 2.0m from the pile line.
Kieran
It is proposed to dredge the area under the piles after a concrete beam is cast, to a level 6.0m below water level. The piles are 11.8m long and top of pile level is 5.73m above water level. This leaves an embedment depth of only 70mm.
This is my concern. I was not involved until after the piles were installed. My thoughts are to not allow any dredging, but this will render the project unworkable.
Anyone any suggestions.
I'm thinking of sand bags in front of the piles to prevent the soil in this area from being removed. This is in Africa so tremie concrete and any solution which requires western technology is not possible. The jetty line is only 2.0m from the pile line.
Kieran