MotorCity
Structural
- Dec 29, 2003
- 1,787
In a text by Braja Das, I came across a discussion of calculating areas and perimeters for pipe and H-piles. He states that the soil plugs formed within these sections during driving should be included when calculating the areas and perimeters for these types of piles. My question is, "WHY?".
I would expect to use the actual area and perimeter of the steel cross section. It does not seem logical that the soil plugs would contribute in any way to the structural capacity of the pile. Is my interpretation incorrect? Any thoughts?
I would expect to use the actual area and perimeter of the steel cross section. It does not seem logical that the soil plugs would contribute in any way to the structural capacity of the pile. Is my interpretation incorrect? Any thoughts?