Lately on projects I've encountered piping installations where risers are supported on every other floor. My local plumbing code indicates this is acceptable only for threaded standard pipe schedule (SPS) pipe. BOCA says vertical supports are required at least at every floor (15' max for steel pipe).
As a commissioning agent, I'm not a guy on a power trip and don't fuel animosity on projects, but find it's very difficult to convince contractors of the requirements. Has anyone else seen this? Are you a pipe fitter and find that adding a friction clamp at every floor is just a nuisance?
As always, feedback is appreciated. -Chas.