Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Pipe Zone Compaction 1

Status
Not open for further replies.

bank

Civil/Environmental
Jan 7, 2003
74
We designed an underground detention system using 30" HDPE pipe. According to our details and ASTM 2321 the trench is supposed to have a minimum clearance between the pipe and the trench wall of 10", backfilled with compacted Class I or II material. The contractor instead set the pipe in a trench almost exactly the width of the pipe OD. In-situ soil in this area is generally fat clay.

When we told him he had to take the pipe out of the ground, widen the trench, and provide the required backfill he asked if he could leave the pipe in place, widen the trench as required, and backfill and compact the Class I or II material. My question is can this work? Can they widen the trench 10" on either side of the HDPE pipe without damaging it, and achieve the required compaction such that the pipe is adequately supported laterally?
 
Replies continue below

Recommended for you

Thanks everybody. The contractor has pulled the pipes out of the ground and is going to re-install them per the contract documents.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor