Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

pipeline line fill calculations : volume correction CTS, CPS, CPL and CTL

Status
Not open for further replies.

lucian7ppl

Petroleum
Apr 6, 2015
1
Hello,
I'm working on a solution for calculating acurate line fill for batch tracking.
My aproach is to look at the measured volume(GOV) of the bathes at flow meters and by knowing the pipeline segment volume(at base conditions) calculate the location of the head and tail of the batches in the segment.
For a pipline segment I know I have to compensate for the effect of temprature and pressure on steel(CTS, CPS) and on liquid(CTL, CPL).
Assuming that I will have flow meter, temperature and pressure measurment only at the beggining and at the end of the segment how should I do these volume corrections?
Should I look only at the current pressure and temperature of liquid from upstream and downstream stations or should I do an average? If it's an average what kind of average and from which location, and for what period of time?
Could you kindly advice in this matter?
Thanks,
George
 
Replies continue below

Recommended for you

If you have a flat line, an average pressure might work, but with large elevation changes that would probably be a waste of time. Pressure will not have as much of an effect as temperature.

Temperature decreases as the log of distance, so a simple numeric average won't work, but you could calculate an appropriate temperature.

Try just using inlet temperature and velocity and work on developing some compensation factors to correct your predictions to actual results. If that doesn't work, you will have to add more instrumentation points.



OMG%20something%20else.png
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor