gravitate
Mechanical
- Aug 17, 2012
- 80
We have had a company do us a quotation for approximately 3km of buried pipework. In their quotation they have stated that for every 12m length of pipe they deliver they will presume 5 cuts on the pipe and 6 welds. Is this some kind of engineering industry normal? What I have done is presume that on average the welds will be every 6 m and added on an additional weld for each fitting/ T peice etc. Their price is double what I had it down for. Is the way I am doing it unrealistic or is theirs OTT